Las Casitas Paving: Progress Update

The paving schedule for Street Section 4 in Las Casitas Fase 2 has been updated to include the following dates for concrete work:

  • Concrete curbs: June 28 – July 15

  • Concrete slabs: July 16 – 28

For detailed information on the scheduled pouring dates for each curb and slab, please see map reference below.

Las Casitas Paving: Progress Update

Additional Details

Curing Period:

Each paved section will require five days to cure before it can be used for vehicular traffic. Roads will be reopened progressively.

Working Hours:

  • Monday to Friday: 8am – 6pm*
  • Saturday: 8am – 2pm
  • Sundays and Holidays: No work.

*Working hours will be extended to 7am – 9:30pm on days when concrete slabs are poured.

Traffic Management:

Flaggers will be present to guide traffic and ensure safe access during the works.